China Construction Qualification Borrowing: Payment Claims Against the Licensed Builder

China construction guide to payment claims by a qualification borrower against the licensed builder, including proof of work, quality and amounts due under the 2026 Supreme Court interpretation.

Statute Art. 3
Construction plans and a stamped project payment document on a desk.

When a contractor uses a licensed construction company’s qualification to bid for or sign a project, the payment dispute may involve more than one contract. China’s Supreme People’s Court now states a specific route for a quality-compliant project: the unit or individual that borrowed the qualification may seek value compensation from the licensed builder by reference to their payment agreement.

This claim is between the qualification borrower and the company whose credentials were used. A separate claim against the project owner has a different test and depends on what the owner knew when signing. The distinction matters when choosing the defendant, documenting completed work, and accounting for payments already received.

The payment route under the 2026 interpretation

Article 3 of the Supreme People’s Court’s Construction Contract Disputes Interpretation II addresses qualification lending. A construction company that lends its qualification, or allows another party to contract in its name, enters into an invalid arrangement. The company cannot recover an agreed fee for lending or use of its qualification.

Where the construction work is quality-compliant, the unit or individual that borrowed the qualification may ask the licensed company to pay value compensation by reference to their agreement on construction payments. The rule gives the borrower a defined claim against the licensed builder. It does not make every stated contract amount automatically payable: the claimant still needs to establish the work, applicable payment terms, amounts due, and the quality condition in the specific dispute.

Prove the arrangement and the completed work

Organize evidence around the relationship between the parties and the work for which payment is claimed. The agreement may be informal or recorded across several documents, so compare bid and tender materials, project authorization, the construction contract, internal project records, payment instructions and correspondence about who would perform the work. The evidence should show who supplied the qualification, who undertook the work and how they agreed to account for construction payments.

Then build a separate project ledger: scope and quantities completed, approved variations, progress measurements, inspection and acceptance records, quality rectification, invoices, payments received, retention and other deductions. Identify the contractual milestone for each amount claimed. Keep the borrower’s claimed construction value distinct from any qualification-lending fee, which Article 3 says is not recoverable.

Quality is a condition of the value-compensation route

Article 3 ties the borrower’s claim to construction quality being qualified. Preserve completion, inspection and acceptance materials, quality supervision records, rectification notices and responses. If only part of the project is complete or accepted, identify the relevant sections and explain how the evidence supports the quality and value of that portion. Do not present an overall completion certificate as proof that every disputed quantity or change order was accepted.

If the owner or licensed builder alleges defects, separate the alleged defect, location, technical requirement, notice date, cure opportunity and cost. Record any remedial work and whether it was jointly inspected. An expert appraisal may be relevant where the parties cannot establish quality or value from the existing records, but the claim should first make clear which quantities and issues actually require technical assessment.

Do not confuse a builder claim with a direct owner claim

Article 4 governs the separate situation where the borrower signed the construction contract in the licensed company’s name and seeks value compensation directly from the project owner. If the owner neither knew nor should have known of the qualification borrowing when it contracted, the borrower cannot bind the owner to that arrangement to obtain payment. If the borrower proves the owner knew or should have known, the court must bring the licensed builder into the case as a third party and considers the owner’s payments and the borrower’s construction work in deciding responsibility.

That owner-knowledge test is not an element of the Article 3 claim against the licensed builder. Conversely, proving a payment agreement with the licensed builder does not by itself establish a direct claim against the owner. Map each contract, defendant, payment and alleged obligation before filing or responding to a claim.

Separate qualification lending from subcontracting

The interpretation also treats transfer of a project or unlawful subcontracting separately. Article 6 allows a recipient of a transfer or unlawful subcontract to seek value compensation from the contracting party by reference to that arrangement, but does not allow that recipient to seek payment or damages from an owner with whom it has no contract relationship under that provision. The project documents and actual relationship matter; the labels used in invoices or site communications do not alone establish which legal route applies.

Payment-claim file checklist

  • Documents showing who lent and borrowed the qualification and who signed or performed each contract.
  • The agreement governing construction scope, payment milestones, settlement, retention and deductions.
  • Daily logs, site access, personnel and equipment records, measurements, approved variations and progress reports.
  • Quality inspections, acceptance materials, defect notices, rectification evidence and any appraisal reports.
  • A reconciliation of amounts billed, paid by the owner, received by the licensed builder, passed on to the borrower and still claimed.
  • A separate analysis of any proposed direct claim against the project owner under Article 4.

Article 3 supplies a route for seeking value compensation from the licensed builder when the work is quality-compliant. The project record determines how much work and payment the evidence supports; the route does not validate the qualification-lending arrangement or turn an agreed qualification fee into construction compensation.

Official source

Sources & trust

How to use this article

This insight is general information for orientation on China-related legal topics. It is not legal advice and does not create an attorney–client relationship. Prefer primary statutes, courts, and official guidance when making decisions.

Editorial Policy · AI Content Policy · Lawyer Verification Policy · Listing standards · Disclaimer · Request a consultation

Share LinkedIn X Email
Shi Peng, Real Property lawyer

About the author

Shi Peng

Hubei Jingli Law Firm. Verified listing on China Law List. Insights are educational and do not create an attorney–client relationship.

Discussion

Join the conversation

Share a professional question or experience. This is not legal advice — no attorney–client relationship is formed by posting here.

Next step

Need counsel on this topic?

Connect with verified real property lawyers across China, or ask a free initial question.

Educational information only — not legal advice. Laws change; consult qualified counsel for your situation. No attorney–client relationship is formed by using this site. See our Disclaimer, Editorial Policy, and AI Content Policy.