In an equipment contract, a supplier’s breach does not automatically require double repayment of a deposit. Article 587 of China’s Civil Code ties the statutory deposit penalty to whether the breach prevents the contract’s purpose from being achieved. The practical question is how the agreed function of the equipment, the type of failure and any remaining usable performance fit together.
That analysis is easier when the contract describes the equipment’s core commercial purpose and separates it from secondary preferences. A clear record of required functions, accepted stages, proposed cure and the value of any usable performance can help both sides assess whether the statutory threshold is met. This guide focuses on that threshold and the contract drafting that supports it.
The statutory test is whether the contract purpose can still be achieved
Article 587 of the Civil Code allows a deposit penalty when a party fails to perform, or performs inconsistently with the agreement, so that the purpose of the contract cannot be achieved. A buyer whose breach has that effect cannot seek return of the deposit; a supplier whose breach has that effect must return twice the deposit. A missed milestone or disputed feature does not by itself establish the statutory condition.
For equipment procurement, identify the result the parties contracted to obtain: the essential production function, capacity, compatibility, safety feature or other core use stated in the agreement. The purpose should be drawn from the contract, technical schedules, commercial proposal and negotiation record together. A broad product label rarely explains which functions were indispensable to the transaction.
Separate essential performance from secondary requirements
Compare the alleged failure with the agreed purpose. Consider whether it affects a core function or a secondary attribute, whether the equipment can perform the agreed work, how much of the transaction is affected, and whether the contract provides a practical cure or replacement route. These facts help explain the effect of the breach; they do not create an automatic checklist that decides every case.
For example, an equipment purchase may combine several machines or stages. A shortfall affecting one accepted unit may have a different effect from a failure that prevents the whole line from operating for its contracted use. State the intended role of each major item and whether each item has independent value. Avoid relying on a generalized statement that any deviation defeats the whole contract purpose.
Consider whether performance can be restored
A proposed repair, replacement or reconfiguration can matter if it is capable of restoring the contracted function within a commercially workable period. Record what remedy was offered, the time and cost, any dependency on the buyer’s site or inputs, and whether the other party reasonably cooperated. A cure proposal does not necessarily erase an earlier breach, but it can be relevant to whether the transaction’s purpose remains achievable.
Keep the analysis tied to the contract. A supplier should explain how the offered cure meets the original specifications and schedule; a buyer should identify which essential requirement remains unmet and why the offer does not solve it. If the parties disagree about performance, preserve the materials needed to assess the disputed function and avoid changing or disposing of relevant equipment without notice where practicable.
Account for accepted partial performance
Article 68 of the Supreme People’s Court’s 2023 contract interpretation addresses accepted partial performance. If one party has performed part of the contract and the other accepted it, the deposit penalty is generally calculated in proportion to the unperformed portion. Applying it to the entire contract is not supported unless the incomplete part makes the contract’s purpose impossible to achieve.
For a multi-unit or staged purchase, identify what was delivered, accepted, paid for, installed or put to use, and what remains outstanding. Explain whether the accepted part serves the commercial purpose on its own or only as part of a complete system. A payment or acceptance record can support the analysis, but neither automatically resolves whether the remaining shortfall defeats the contract purpose.
Keep the deposit remedy distinct from other remedies
Where the parties agreed both on a deposit and liquidated damages for breach, Article 588 allows the non-breaching party to choose one remedy for that breach. It does not permit both amounts to be collected automatically simply because both clauses appear in the contract. Other contractual remedies for non-conforming performance may remain relevant depending on the agreement and facts.
State clearly whether a payment is intended to have deposit character, what obligation it secures, how it relates to the contract price, and whether liquidated damages address a different loss or the same breach. Distinguish an advance payment from a statutory deposit and avoid describing every payment as a “deposit” without specifying the parties’ intent and the applicable remedy.
Evidence and drafting checklist
- Contract language identifying the core commercial purpose and essential functions of each major equipment item.
- Technical schedules and proposal materials showing which capacities, interfaces and safety requirements were agreed.
- A deposit clause stating its character, secured obligation, amount, payment date and relationship to the price.
- Records of performance accepted, amounts paid, outstanding items and whether partial performance has independent utility.
- Written cure or replacement proposals, reasons for acceptance or rejection, and the expected time to restore essential functions.
- A remedy analysis selecting the deposit or liquidated-damages clause for the same breach, with any separate claim identified.
The statutory question is not whether the equipment disappointed one party. It is whether the breach, measured against the agreed purpose and any accepted or curable performance, prevents that purpose from being achieved.