China Equipment Sales: Inspection, Acceptance, and Defect Notices

China equipment purchase guide to inspection periods, defect notices, commissioning evidence and the effect of a signed delivery record under Civil Code Articles 620–623.

Statute Art. 620
Industrial equipment beside a stamped delivery and inspection record.

In an equipment purchase, signing a delivery note can affect later arguments about quantity, model, specifications, and visible defects. China’s Civil Code requires the buyer to inspect within the agreed period or, if none is set, in a timely manner. A signature does not necessarily resolve a problem that could only appear during commissioning or normal operation.

The notice rules depend on the contract’s inspection terms, the kind of defect, and when it could reasonably be found. Articles 620–623 address inspection and notice periods, short inspection windows, and the effect of a signed delivery record. Buyers and suppliers can reduce disputes by separating arrival checks from performance tests and preserving a clear written record of each stage.

Separate delivery checks from performance testing

Article 620 of the Civil Code says a buyer must inspect the equipment within the period the parties agreed. If there is no agreed period, inspection must take place in a timely manner. For industrial machinery, a useful contract can distinguish checks available at delivery—such as count, model, serial number, packaging condition and visible damage—from tests that require installation, calibration, trial operation or integration with another system.

Specify who performs each check, what documents or test methods apply, whether a sample or every unit is inspected, and what evidence records the result. Tie acceptance to objective technical requirements in the contract and its appendices. A general phrase such as “inspection on delivery” may leave the parties arguing about whether it covered only appearance or also operational performance.

Give written notice within the applicable period

Under Article 621, when the contract sets an inspection period, the buyer must notify the seller within that period of a quantity or quality mismatch. If the buyer does not give notice in time, the equipment is generally deemed to conform on those points. Where no period is agreed, the buyer must notify the seller within a reasonable time after discovering, or when it should have discovered, the mismatch. The Code also sets a two-year outer period from receipt where no quality warranty period applies. A stated warranty period takes the place of that two-year period. If the seller knew or should have known of the non-conformity, the statutory notice limits do not apply.

These are notice rules, not a universal two-year inspection allowance. A buyer should report a suspected defect promptly once it appears, even if the full cause or repair plan is still under investigation. The notice can identify the equipment, delivery, observed symptom, test result and immediate request, then reserve a fuller technical explanation after joint inspection.

A very short inspection window may cover only visible defects

Article 622 addresses inspection periods too short for a comprehensive examination given the nature of the goods and ordinary course of dealing. Such a period is treated only as the time to object to apparent defects. The Code also says a contract inspection or quality-warranty period shorter than a period required by applicable laws or administrative regulations gives way to the required period.

For equipment that must be installed or operated before performance can be assessed, record when commissioning began, the operating conditions, alarms or failures, test data and the date the issue became detectable. The contract should say how the parties will handle access, preservation, repeat tests and expert inspection while they investigate.

Read a signed delivery record narrowly and carefully

Under Article 623, if the parties did not agree on an inspection period and the buyer signs a delivery note or confirmation stating the quantity, model and specifications, the buyer is presumed to have inspected the quantity and apparent defects. Evidence can rebut that presumption. A signature should therefore identify what was actually checked and any limits on the check. If equipment was received in sealed packaging, under reservation, or before testing, say so on the delivery record instead of relying on a later explanation.

A delivery signature is not the same as a complete commissioning certificate. Separate forms for receipt, installation, trial operation and final performance acceptance help show what was known at each stage. If the supplier needs a signed receipt before unloading, the form can expressly state whether it confirms custody only or also records completed inspection.

Connect the notice to a specific remedy

Article 617 provides that where delivered goods fail to meet the agreed quality requirements, the buyer may seek the seller’s contractual liability under Articles 582–584. Depending on the agreement and circumstances, that may involve repair, replacement, re-performance, a price reduction or compensation. The Supreme People’s Court’s Interpretation on Sales Contract Disputes also addresses remedies for quality objections and reasonable repair costs.

Keep the requested remedy proportionate to the problem and the contract. Do not discard, alter or extensively repair disputed equipment before giving the other party a reasonable chance to inspect it, unless urgent safety or mitigation needs require action. Preserve the failed component, photographs, test logs, maintenance records, repair invoices and communications explaining why immediate action was necessary.

Equipment acceptance record checklist

  • Contract specifications, drawings, applicable standards, test protocol and agreed inspection or warranty periods.
  • Delivery note listing count, model and serial numbers, package condition, visible damage and any express reservation.
  • Installation and commissioning dates, operating conditions, calibration records, alarms and test data.
  • Dated written notices describing each suspected mismatch and the date it was first found or reasonably detectable.
  • Joint-inspection invitations, sample retention, expert reports, repair steps and a record of any parts replaced or modified.
  • Acceptance documents that distinguish receipt, interim testing and final sign-off against stated performance criteria.

Disputes often turn on what the buyer could observe, when it became observable, and what the parties documented. A clear testing schedule and prompt, specific notices make those facts easier to establish for both sides.

Official sources

Sources & trust

How to use this article

This insight is general information for orientation on China-related legal topics. It is not legal advice and does not create an attorney–client relationship. Prefer primary statutes, courts, and official guidance when making decisions.

Editorial Policy · AI Content Policy · Lawyer Verification Policy · Listing standards · Disclaimer · Request a consultation

Share LinkedIn X Email
Keqiang Wang, Real Property lawyer

About the author

Keqiang Wang

Hubei Yuanlai Law Firm. Verified listing on China Law List. Insights are educational and do not create an attorney–client relationship.

Discussion

Join the conversation

Share a professional question or experience. This is not legal advice — no attorney–client relationship is formed by posting here.

Next step

Need counsel on this topic?

Connect with verified real property lawyers across China, or ask a free initial question.

Educational information only — not legal advice. Laws change; consult qualified counsel for your situation. No attorney–client relationship is formed by using this site. See our Disclaimer, Editorial Policy, and AI Content Policy.