In a cross-border contract, “arbitration venue” can mean several different things: the institution that administers the case, the legal seat of arbitration, or the place where witnesses and counsel attend a hearing. Those choices can overlap, but they do different work. A contract that names only a convenient hearing city may leave the legal seat unclear.
This guide focuses on one practical drafting issue: how to separate the legal seat from the physical or online hearing arrangement. Under China’s revised Arbitration Law, in force since 1 March 2026, the seat has a defined role in foreign-related arbitration. Institution rules can separately address where and how hearings take place.
Three locations that should not be collapsed into one
The administering institution receives and manages the case under its rules. Its office address may be relevant to administration, but it does not answer every question about the arbitration's legal location.
The legal seat is the juridical place of arbitration. For foreign-related arbitration, Article 81 of China's revised Arbitration Law allows the parties to agree on the seat in writing. Unless they agree otherwise on the law governing arbitral procedure, the seat is the basis for identifying that law and the courts with jurisdiction; the award is deemed made at the seat. If the parties leave the seat unspecified or unclear, the agreed arbitration rules determine it, and if those rules do not, the tribunal determines it by reference to the convenience of resolving the dispute.
The hearing place or format concerns logistics: a room in one city, a different location under the applicable rules, or a remote or hybrid hearing. It does not automatically replace a separately chosen seat. Check the institution's rules and state the parties' intended arrangement in language those rules recognize.
Why the seat needs its own words
The revised Arbitration Law took effect on 1 March 2026. Its foreign-related arbitration chapter gives the seat express statutory consequences. A clause that names an institution and a hearing city but does not identify which one is the legal seat may leave that important choice to the institution's rules or, if they do not resolve it, to the tribunal.
The statute's default sequence is deliberate: first the parties' written agreement, then the selected rules, then a tribunal determination if the rules are silent. Do not rely on a venue label in a business template to answer a question that the rules treat separately. If the contract is foreign-related and the parties want a particular Chinese or overseas place as the seat, identify it clearly and confirm that the chosen rules operate consistently with that choice.
The seat is not the governing law of the commercial contract. The parties may separately choose the law governing the contract and, under Article 81, may agree on a law governing arbitral procedure. Those are distinct choices and should not be bundled into a single phrase such as “arbitration in [city] under [law]” without stating what each part means.
Check the chosen institution's rule on hearing place
Rules can give a different answer for the hearing room than for the seat. CIETAC's 2024 Arbitration Rules illustrate the distinction. Article 7 addresses the place of arbitration: the parties' agreement prevails, and in the absence of a clear agreement the rule supplies a default linked to CIETAC or its administering sub-commission or arbitration center, with a possible determination of another location. Article 36 separately addresses the place of oral hearings. Article 37 permits an in-person, remote or other electronic hearing after the tribunal consults the parties and considers the case.
This is an example from one institution's rules, not a universal rule for every Chinese commission. Before naming an institution, read the version of its rules that would apply to the contract and check how it distinguishes the place of arbitration, the hearing location, remote proceedings, and authority to set or change hearing arrangements.
Choose hearing arrangements around the dispute
Once the legal seat and institution are clear, decide whether the contract should also state a default hearing place or leave that choice to the rules and tribunal. Consider where the likely witnesses, records, technical evidence and representatives are located; whether interpretation is needed; travel time and cost; secure handling of confidential material; and whether a remote hearing would work for the evidence and participants.
If the parties expect an in-person hearing in a particular city, state that it is the hearing place and avoid wording that could also be read as the legal seat. If the parties prefer flexibility, specify the governing rule and a consultation process rather than listing several cities without a hierarchy. For online or hybrid proceedings, decide which participants must attend in person, how identity and confidentiality will be handled, and how exhibits and the hearing record will be transmitted.
Do not assume that an agreed physical room guarantees an in-person hearing in every circumstance. The applicable rules may preserve powers for the tribunal or institution to manage exceptional situations. Read the exception language and decide whether the parties need a tailored provision.
A focused drafting sequence
- Name the administering institution accurately and identify the applicable rules and version.
- State separately the legal seat of the arbitration, if the dispute is foreign-related and a particular seat is intended.
- State whether a named city is the seat, the hearing place, or both; do not use “venue” alone where that distinction matters.
- Check how the rules determine the seat and hearing place when the clause is silent, and whether a tribunal may select another location.
- Choose whether hearings may be remote or hybrid, and leave room for tribunal decisions permitted by the selected rules.
- Review the contract's governing-law clause and any agreement on the law governing arbitral procedure as separate provisions.
- Check how notices, language, translation, witness attendance and evidence handling work with the chosen location and rules.
Illustrative clause structure
A drafting team can use separate sentences rather than one ambiguous “venue” phrase:
“Any dispute shall be administered by [exact institution name] under its [identified rules and version]. The legal seat of the arbitration is [city and country]. The place and format of any oral hearing shall be determined under [identified rule or an express hearing-place agreement].”
This is a structure for discussion, not a ready-to-sign clause. The correct terms depend on the transaction, whether the arbitration is foreign-related, the parties' chosen institution and rules, and the consequences they intend for procedural law and court supervision.
Primary sources
- Revised Arbitration Law of the People's Republic of China, especially Articles 27 and 81.
- Ministry of Justice notice on the revised Arbitration Law, which states the law took effect on 1 March 2026.
- CIETAC Arbitration Rules (2024, English), Articles 7 and 36–37, as one institution-specific illustration.