When a fixed-price construction contract in China ends before the project is complete, the parties may still disagree about payment for the compliant work already performed. Article 10 of the Supreme People’s Court’s 2026 construction-contract interpretation gives courts a method for valuing that portion when the contract does not settle the issue and the parties cannot reach agreement.
The method compares the value of the quality-compliant completed work with the value of the whole project using local pricing standards or construction-industry norms, then applies that ratio to the contract’s fixed total price. The scope, quality, and measurement records therefore matter alongside the headline contract sum.
When the Article 10 method applies
Article 10 addresses a specific situation: a fixed-total-price construction contract has been terminated, work has been completed to an acceptable quality, the parties did not agree how to price that completed portion, and they cannot reach agreement. In those circumstances, a court may use local construction-administration pricing standards or methods, or relevant construction-industry norms published at the location and time the contract was made, to calculate the share represented by the compliant completed work.
The court may then multiply that share by the contract’s fixed total price to determine the amount for the completed portion. This is a valuation method for unfinished work after termination. It does not automatically award the full contract price, decide every damages claim, or resolve payment rights for unrelated subcontractors.
Define the completed scope before calculating
Start with the signed contract, technical specifications, drawings, scope schedules, and any agreed changes. Identify the work actually performed by the termination date and separate it from unfinished items, rejected work, and work outside the agreed scope. A progress percentage stated in a meeting record is useful only if it can be tied to identifiable quantities and the contract documents.
Preserve dated site logs, measurement sheets, inspection reports, test results, progress certificates, photographs, delivery records, and notices of defects or corrections. Keep records showing which party prepared and approved each measurement. If the parties dispute the physical quantity or quality of work, that factual dispute must be addressed before the Article 10 ratio can be applied.
Support the ratio with local pricing evidence
The interpretation points to pricing standards or methods issued by the construction-administration department where the project is located and relevant industry norms, using those published when the contract was concluded. Keep the version and publication date of each standard. Explain how the completed compliant work and the full project were measured on a consistent basis.
Where the project uses different work packages or technical specifications, show how each package enters the numerator and denominator of the ratio. If a valuation relies on an expert calculation, provide its source documents, assumptions, quantity takeoffs, and treatment of approved variations. Do not treat a simple percentage of elapsed time or money already spent as the statutory ratio without evidence that it reflects the relative value of the completed work.
Keep other contract issues in separate calculations
Article 10 concerns the price of quality-compliant work completed under a terminated fixed-total-price contract. Defective work, repair costs, delay losses, disputed variations, retention, and payments already made may require separate analysis under the contract and other applicable rules. Reconcile invoices and prior payments against the completed-work valuation so the same amount is not counted twice.
For a practical file, prepare a termination timeline, a scope-to-evidence table, a quality record, the applicable local pricing materials, and a transparent calculation of the ratio and resulting amount. Article 23 says the 2026 interpretation applies to first-instance construction-contract cases newly accepted after it took effect on June 30, 2026. Confirm the case’s filing and acceptance status, contract terms, and project records with China construction counsel. See the Supreme People’s Court’s Interpretation II on Construction Contract Disputes, Articles 10 and 23.